³ªÀÌÁö¸®¾Æ Àü·Â°ø»ç(Power Holding Company of Nigeria, PHCN)´Â ÃÖ±Ù, ³ªÀÌÁö¸®¾Æ ¼öµµ ¾ÆºÎÀÚ(Abuja)¿¡ °Ç¼³µÉ ¾Æ·¡ º¯Àü¼Ò 2°÷¿¡ ´ëÇÑ º¯Àü¼³ºñ °ø±Þ ¹× ¼³Ä¡¸¦ À§ÇÑ ±¹Á¦ÀÔÂûÀ» ½Ç½ÃÇÑ´Ù°í ¹ßÇ¥ÇßÀ½.

- One(1) New 2 X 60MVA, 132/33KV Substation at Karu in Abuja

- One(1) New 2 X 60MVA, 132/33KV Substation at Kubwa in Abuja


º¯Àü¼³ºñ °ø±Þ ¹× ¼³Ä¡ ±âÇÑÀº ³«Âû ÀÌÈÄ 15°³¿ùÀ̸ç, ³«Âû ±â¾÷Àº À§ 2°÷ÀÇ º¯Àü¼Ò °Ç¼³¿¡ ÇÊ¿äÇÑ º¯Àü¼³ºñ ÀüºÎ¸¦ ¸ðµÎ °ø±Þ ¹× ¼³Ä¡ÇÏ¿©¾ß ÇÔ.

À̹ø ÀÔÂûÀº ¡°Procurement under IBRD Loans and IDA Credits, May 2004 edition¡± »óÀÇ ¼¼°èÀºÇà °¡ÀÌµå ¶óÀο¡ ±ÔÁ¤µÈ ±¹Á¦ °æÀïÀÔÂû ÀýÂ÷¿¡ µû¶ó Ä¡·ïÁö¸ç, ´ÙÀ½°ú °°Àº ÃÖ¼Ò ÀÚ°Ý ±âÁØÀ» °®Ãá ±â¾÷µéÀº ´©±¸³ª ÀÔÂû¿¡ Âü°¡ÇÒ ¼ö ÀÖÀ½.

¤· Average annual turnover(supply and installation of power equipment) of US$ 20 million, calculated as total certified payment received for contract in progress or completed, within the last five(5) years


¤· Cash flow amount of US$ 3.3 million or equivalent


¤· Five(5) years of experience under supply and installation contracts of substations equipment in the role of contractor or subcontractor and execution of at least two(2) contracts of similar nature and complexity within the last five(5) years, each with a value of at least US$ 14 million.


ÀÔÂûÈñ¸Á ±â¾÷µéÀº ³ªÀÌÁö¸®¾Æ ½Ã°£À» ±âÁØÀ¸·Î ÆòÀÏ ¿ÀÀü 10½ÃºÎÅÍ ¿ÀÈÄ 5½Ã±îÁö ¾Æ·¡ (ÁÖ¼Ò 1)À» Á¢ÃËÇÏ¿© Ãß°¡ÀûÀÎ ÀÔÂû Á¤º¸¸¦ ÀÔ¼öÇϰųª ÀÔÂû ¼­·ù¸¦ È®ÀÎÇÒ ¼ö ÀÖÀ¸¸ç, ¼­¸é ½Åû¼­¿Í ÇÔ²² ³ªÀÌÁö¸®¾Æ Àü·Â°ø»ç(PHCN)¸¦ ¼öÃëÀÎÀ¸·Î ÇÏ´Â 13,000 ³ªÀ̶ó ¶Ç´Â ¹Ì$ 100 Â¥¸® ÀºÇà º¸Áõ¼öÇ¥¸¦ ¾Æ·¡ (ÁÖ¼Ò 2)¿¡ Á¦ÃâÇÏ¸é ¿µ¹® ÀÔÂû¼­·ù¸¦ ±¸¸ÅÇÒ ¼ö ÀÖÀ½.

ÀÔÂûÈñ¸Á ±â¾÷µéÀº ¶ÇÇÑ, »ó±â ±Ý¾× ¿Ü¿¡ Ãß°¡·Î ³ªÀÌÁö¸®¾Æ Àü·Â°ø»ç(PHCN-PMU)¸¦ ¼öÃëÀÎÀ¸·Î ÇÏ´Â 13,000 ³ªÀ̶ó ¶Ç´Â ¹Ì$ 100 Â¥¸®(À¯·´ ¹× ¼­ºÎ ¾ÆÇÁ¸®Ä«) ¶Ç´Â 26,000 ³ªÀ̶ó ¶Ç´Â ¹Ì$ 200 Â¥¸®(±âŸ Áö¿ª) ÀºÇà Áö±Þ ¸í·É¼­(Demand Draft)¿Í ÀÔÂû¼­·ù ¼ÛºÎ¸¦ ¿äûÇÏ´Â ÀÔÂûÈñ¸Á ±â¾÷ÀÇ Letter Head µîÀ» 2007. 1. 31(¼ö) ±îÁö ¾Æ·¡ (ÁÖ¼Ò 1)¿¡ Á¦ÃâÇÏ¸é ¿µ¹® ÀÔÂû¼­·ù¸¦ Ư»ç ¿ìÆíÀ¸·Î ¹Þ¾Æ º¼ ¼ö ÀÖÀ½.


ÀÔÂû ¼­·ù´Â ¹Ì$ 25¸¸ ¶Ç´Â ÀÌ¿¡ »óÀÀÇÏ´Â ÀÚÀ¯ ÅÂȯ ÅëÈ­ ¶Ç´Â ³ªÀ̶óÀÇ ÀÔÂû º¸Áõ±Ý°ú ÇÔ²² 2007. 3. 8(¸ñ) 12:30PM(³ªÀÌÁö¸®¾Æ ½Ã°£ ±âÁØ) ±îÁö ¾Æ·¡ (ÁÖ¼Ò 1)¿¡ µµÂø½ÃÄÑ¾ß ÇÔ.


ÀÔÂû ¼­·ù´Â ÀÔÂûÀÚ ¶Ç´Â ´ë¸®ÀÎ ÀÔȸ ÇÏ¿¡ ¾Æ·¡ (ÁÖ¼Ò 1)¿¡¼­ 2007. 3. 8(¸ñ) 12:30PM(³ªÀÌÁö¸®¾Æ ½Ã°£ ±âÁØ), °³ºÀµÉ ¿¹Á¤ÀÓ.


( ÁÖ¼Ò 1 )

Bayo Adeniyi
Manager, Project Management Unit,

Power Holding Company of Nigeria PLC

7 Kampala Street, Wuse II, Abuja, NIGERIA

Tel/Fax : 234?9) 413 6684, 413 6685

E-mail : bayoadeniyi@nepapmu.org


( ÁÖ¼Ò 2 )

Alhaji Shuaibu Magida

Coordinator Liaison Unit

Power Holding Company of Nigeria PLC

Plot 441, Zambezi Crescent, Maitama, Abuja, NIGERIA
ű¹ ¹«¿ª µ¿Çâ ¹× Àü¸Á
±â¼úÇ¥ÁØ¿ø, ½Å±â¼úÁ¦Ç° ÀÎÁõ-Çõ½ÅñéÐê Áö¿øÃ¥ ¼³¸íȸ °³ÃÖ